November 2021-February 2023: Car park roadway upgrades
May 2022: Skate park/pump track works commence
August 2022: Skate park/pump track works complete
December 2022: Skate park/pump track open
January 2023: Basketball court works commence
February 2023: Basketball court works complete
Landscaping works commence
April 2023: Landscaping works complete
February 2024: Splash park works commence.
(Note: Correct as of 2024)