Bald Hill Activation Project

Share Tweet Print More Options

Step 1: The Bacchus Marsh 1000+ 

This project will see the installation of 1000+ steps travelling up Bald Hill. It will also use the existing walking trail on Bald Hill to create a place for exercise, recreation, as well as art spaces.  

Moorabool Shire Council is undertaking a reconstruction of the existing Lerderderg Track via funding from Regional Development Victoria. The $750,000 project will see the construction of over 1000 Steps and lookout. 

The State Government grant will be used to begin the consultation process which will inform the design of the project, ahead of a potential construction start date of late 2021.

To provide your comments, click on the 'Have Your Say' button below:  

Have Your Say

 

          

Images are an artists impression of the Bacchus Marsh 1000+ project. 

 

Consultation and concept design: Oct - Dec 2020

Council is consulting with local landowners, the wider community and key stakeholders.

 

Detailed design, tender and construction: January 2021 to August 2022

Click to view the Bald Hill Activation Plan report.

 

Further exciting opportunities and projects to come as part of the Bald Hill Activation Project. 