October 2022 Final design completed
November 2022 Tender opened
6 December 2022 Construction tender closed
22 December 2022 Construction contract awarded
Mid-January 2023 Construction started
End of November 2023 Expected practical completion date
Mid-January 2024 Centre open and operational