November 2021-February 2023: Car park roadway upgrades
December 2021: Draft skate park design community consultation
January-February 2022: Draft skate park design - Design consultation
March 2022: Agreement of final skate park design
April 2022: Basketball court draft design
May 2022: Skate park/pump track works commence
August 2022: Skate park/pump track works complete
December 2022: Skate park/pump track open
January 2023: Basketball court works commence
February 2023: Basketball court works complete
Landscaping works commence
April 2023: Landscaping works complete
Playground works commence
(Note: Correct as of 19 December 2022)