Apr 2017 |
AEMO publishes the first report, the Project Specification Consultation Report (PSCR) which seeks feedback and advice on the identified need for new transmission infrastructure. |
Dec 2018 |
AEMO published Project Assessment Draft Report (PADR) that assessed the technical and economic feasibility of options to improve transmissions options in western Victoria. |
31 Jan 2019 |
CEO and council staff have an Initial meeting with AEMO. Project report in draft and no final decision made on which project will be put to tender. |
1 Feb 2019 |
Council requests potential alignment from AEMO. Provided very high-level map from PADR. |
Feb 2019 |
Advert appears in local paper:

|
Feb-May 2019 |
Council seeks further clarification on the preferred alignment and its impact on Moorabool Shire Council. |
6 June 2019 |
Council meets with AEMO to discuss the project in more detail |
26 June 2019 |
Council provides a detailed submission to AEMO.(PDF, 166KB) Council’s view was that the project needs to be conducted in a manner that has the least impact on our residents, our existing landscape, the natural environment, farming activities, our towns and the growth projected for the Shire. Council reiterated that the most appropriate way to address these concerns would be through the undergrounding of the powerlines, ideally for the extent of the project or at least in part. |
28 June 2019 |
Submission supplied to all Federal and State Members. |
9 July 2019 |
Council Staff meet with AEMO to discuss the Submission |
19 July 2019 |
Western Victoria Renewable Integration Report – Project Assessment Conclusions Report (PACR) published. This report confirms that the preferred option is a new 500kV line from Sydenham to North Ballarat. |
29 July 2019 |
Council does media release and the project is in the Moorabool News. |
1 Oct 2019 |
Council officers receive briefing from AEMO on PACR
|
22 Oct 2019 |
Council provides second submission(PDF, 537KB) to AEMO focussed on potential fire risk. Submission reiterates the request of underground. |
17 Dec 2019 |
AEMO selected Mondo, the commercial division of the AusNet Services Group to plan, design, construct, own, operate and maintain the Western Victoria Transmission Network Project. |
18 Dec 2019 |
Mondo wrote to Council stating they will be in touch in the new year to discuss project. |
18 Dec 2019 |
Council wrote to Mondo(PDF, 599KB) providing our submissions and reiterating the need to understand where the alignment was proposed to be. |
20 Dec 2019 |
Mondo/AusNet acknowledging letter. |
13 Mar 2020 |
Council had first meeting with Mondo/AusNet. Council first told that letters were going to be sent to landowners (this got put on hold due to COVID-19). |
1 Apr 2020 |
Moorabool holds first meeting with all affected councils |
28 Apr 2020 |
Joint letter from Moorabool, Melton and Hepburn raising concerns(PDF, 311KB) |
4 May 2020 |
Letter from AusNet acknowledging receipt of letter |
1 June 2020 |
AusNet advises council officers that letters were sent to 120 land owners. Phone calls commenced the following week. |
3 June 2020 |
AusNet provides briefing to Councillors |
19 June 2020 |
Victorian EES Referral accepted by Planning Minister
Referral documents:
- Area of interest(PDF, 1MB)
- Detailed map(PDF, 8MB)
- Protected areas(PDF, 895KB)
- Zone and overlay plans(PDF, 5MB)
- Biodiversity plans(PDF, 3MB)
- Public and private land(PDF, 1MB)
- Stakeholder engagement(PDF, 421KB)
- Rare and threatened species(PDF, 103KB)
- Heritage places(PDF, 899KB)
- Referral(PDF, 558KB)
|
20 June 2020 |
Community held meeting in Myrniong |
26 June 2020 |
Second joint letter from Moorabool, Melton and Hepburn councils(PDF, 376KB) |
27 July 2020 |
Letter to Minister for Planning from Moorabool, Melton, Hepburn and Ballarat councils(PDF, 346KB) |
29 July 2020 |
CEOs from Moorabool, Melton and Hepburn met with Executive team from AusNet and AEMO to discuss issues raised in first joint letter |
4 Aug 2020 |
Planning Minister confirms EES will be required for project
Minister’s decision documents:
|
6 Aug 2020 |
Federal EPBC Referral accepted and open for public comment
EPBC Referral documents:
|
13 Aug 2020 |
Moorabool CEO writes to Australian Energy Market Operator(PDF, 239KB) asking for an expanded justification on the cost comparison used to rule out underground as an option |
14 Aug 2020 |
Moorabool provides submission to EPBC referral(PDF, 292KB) |
18 Aug 2020 |
A joint letter from Moorabool, Melton, Hepburn and Ballarat councils raising concerns(PDF, 339KB) |
25 Aug 2020 |
Mayor David Edwards writes to Victorian MPs(PDF, 218KB) seeking their support to ask AusNet to bury the transmission line |
2 Sept 2020 |
EPBC Decision(PDF, 380KB) – controlled action assessed under the bilateral agreement with the Victorian Government |
4 Sept 2020 |
Letter to Federal Minister for Energy and Emission Reduction(PDF, 237KB)
|
4 Sept 2020 |
Letter to Federal Minister for Environment(PDF, 235KB) |
16 Sept 2020 |
Letter from Australian Energy Market Operator(PDF, 93KB) in response to 13 August 2020 letter regarding underground options |
23 Sept 2020 |
Community Session 1: Understanding the Environment Effects Statement (EES) process
Presented by Jack Krohn, Senior Impact Assessor, Department of Environment, Land, Water and Planning |
25 Sept 2020 |
Council releases independent report(PDF, 5MB) that compares aboveground with underground
|
8 Oct 2020 |
Community Session 2: Understanding compulsory land acquisition and compensation
Presented by Tony Rutherford, Shaun Whittaker and Jackson Dyer from Mills Oakley Law Firm. |
9 Oct 2020 |
Letter to AEMO requesting further information on AC/DC, loss of social licence, and commercial matters(PDF, 297KB) in response to 16 September 2020 letter |
21 Oct 2020 |
Community Session 3: Energy Safe Victoria Part 1 - Safety and High Voltage Transmission Lines
Presented by Brett Fox and Gavin Jackson from Energy Safe Victoria |
16 Nov 2020 |
Letter from Australian Energy Market Operator(PDF, 108KB) in response to concerns raised in 9 October 2020 letter |
Dec 2020 |
Minister for Planning issues final scoping requirements for EES |
3 Dec 2020 |
Community Session 3: Energy Safe Victoria Part 2 - Farming and High Voltage Transmission Lines
Presented by Brett Fox and Gavin Jackson from Energy Safe Victoria |
9 Dec 2020 |
Community Session 4: AEMO explains RiT-T and findings
Presented by Tony Chappel, Alex Wonhas, Greg Thorpe & Alistair Parker |
13 Jan 2021 |
Letter to John Brumby(PDF, 250KB) regarding impact of transmission lines on the Central Victorian Goldfields World Heritage Bid |
15 Feb 2021 |
Council commissions independent local economic impact assessment(PDF, 55MB) |
17 Feb 2021 |
Letter to Australian Energy Regulator(PDF, 241KB) raising concerns with RIT-T process in light of local economic impact assessment |
24 Feb 2021 |
AusNet Services announces corridors and next steps for determining final route |
2 Mar 2021 |
AusNet Services release their Environment Effects Statement Consultation Plan and establish a Community Consultation Group, CCG minutes can be accessed via their website
|
16 Mar 2021 |
Letters to Australian Energy Regulator(PDF, 316KB) and Australian Energy Market Operator requesting re-application of RIT-T process
|
29 Apr 2021 |
Letter from Australian Energy Regulator(PDF, 303KB) in response to concerns with RIT-T process raised in 16 March 2021 letter |
11 May 2021 |
Letter from Australian Energy Market Operator(PDF, 87KB) in response to re-application of RIT-T process requested in 16 March 2021 letter |
13 June 2021 |
Moorabool releases independent report comparing impacts of underground versus overhead transmission line |
16 June 2021 |
Moorabool Shire Council passes resolution to continue advocating for proper consideration of undergrounding the transmission line
|
30 June 2021 |
AusNet Services announces the proposed single overhead corridor and next steps for determining the final route |
20 Sept 2021 |
Letter from Council Officers raising concerns over Community Consultation Group Terms of Reference
|
Late-Sept 2021 |
AusNet Services hosts live webinars with environmental and technical specialists which are now available to watch on their website
|
9 Nov 2021 |
Letter from Council Officers raising concerns over community engagement processes and reporting |
11 Nov 2021 |
Community Session 1: Update on the Environment Effects Statement (EES) process
Presented by Jack Krohn, Senior Impact Assessor, Department of Environment, Land, Water and Planning |
23 Nov 2021 |
Moorabool Mayor writes to the Premier of Victoria(PDF, 221KB) advocating for undergrounding the transmission line |
25 Nov 2021 |
Community Session 2: Understanding the Renewable Energy Zones (REZs) in Western Victoria
Presented by Ben Ferguson, Director of Renewable Energy Zones Development Branch, Department of Environment, Land, Water and Planning |
26 Nov 2021 |
AusNet Services announces proposed final route for an overhead transmission line and releases Underground Construction Summary eliminating underground options |
26 Nov 2021 |
Moorabool Mayor Cr Tom Sullivan issues media release in response to AusNet's final route announcement |
14 Dec 2021 |
Moorabool Mayor writes to politicians(PDF, 371KB) regarding unacceptable setback distances between the transmission line and private residences |
22 Dec 2021 |
Moorabool Shire adopts High Voltage Transmission Line Setback Policy(PDF, 150KB) at an unscheduled Meeting of Council |
9 Mar 2022 |
Community Session: Preparing a submission to an Environment Effects Statement (EES) pubic review
Presented by Louise Hicks, Barrister, and Jack Krohn, Senior Impact Assessor, Department of Environment, Land, Water and Planning
|
4 Apr 2022 |
Moorabool CEO writes to AusNet(PDF, 349KB) requesting a formal retraction of the unverified findings in their Underground Construction Summary report, released in November 2021 |